Critical Risk Factors Associated with Schedule Delays in Gas Processing Facility Projects: Case Study in Indonesia

2

조회

0

다운로드

1

인용

0

참고문헌

키워드

초록

Purpose: This research intends to provide project stakeholders with a thorough understanding of the risk landscape in gas processing projects from project owner's perspective, allowing them to navigate the maze of problems and ensure project success, thereby promoting energy security and economic growth. Design/methodology/approach: Survey employing focus group discussion (FGD) and questionnaires has been used empirically to identify significant risk factors in the Indonesian gas processing facility project. At first literature research revealed a total of 122 risk variables, of which 97 were validated in FGD by a panel of experts to have effect on the gas processing facility project. Then, questionnaires comprising 97 verified risk variables were delivered to 40 respondents, of whom 33 provided their feedback about the probability and impact of those risks on project schedule performance. The resulting data was evaluated using statistical descriptive analytic techniques, and the study quantifies the relative influence of each risk factor with the use of statistical tools SPSS 28. Findings: This paper found that Contractor financial problem and risks related to virus pandemic are prominent risk factors. Additional significant variables encompass engineering, procurement, construction, and commissioning (EPCC) related risk factors. Research limitations/implications: Further analysis still needs to be performed to explore how project critical risk findings affect cost and quality in other upstream oil and gas projects, and also in projects with different spectra such as in oil and gas downstream sectors. Originality/value: This study comprehensively identifies and analyzes key risks and further investigates the interdependencies and cascading effects of these risks on gas processing facility project, shedding light on their synergistic amplification of schedule burdens.

Abstract

Purpose: This research intends to provide project stakeholders with a thorough understanding of the risk landscape in gas processing projects from project owner's perspective, allowing them to navigate the maze of problems and ensure project success, thereby promoting energy security and economic growth. Design/methodology/approach: Survey employing focus group discussion (FGD) and questionnaires has been used empirically to identify significant risk factors in the Indonesian gas processing facility project. At first literature research revealed a total of 122 risk variables, of which 97 were validated in FGD by a panel of experts to have effect on the gas processing facility project. Then, questionnaires comprising 97 verified risk variables were delivered to 40 respondents, of whom 33 provided their feedback about the probability and impact of those risks on project schedule performance. The resulting data was evaluated using statistical descriptive analytic techniques, and the study quantifies the relative influence of each risk factor with the use of statistical tools SPSS 28. Findings: This paper found that Contractor financial problem and risks related to virus pandemic are prominent risk factors. Additional significant variables encompass engineering, procurement, construction, and commissioning (EPCC) related risk factors. Research limitations/implications: Further analysis still needs to be performed to explore how project critical risk findings affect cost and quality in other upstream oil and gas projects, and also in projects with different spectra such as in oil and gas downstream sectors. Originality/value: This study comprehensively identifies and analyzes key risks and further investigates the interdependencies and cascading effects of these risks on gas processing facility project, shedding light on their synergistic amplification of schedule burdens.

참고문헌 (62)

  1. Abd El-Karim, M. S. B. A., "Identification and assessment of risk factors affecting construction projects", HBRC Journal, 13(2), pp.202~216 (2017)[DOI]
  2. Abdou, A. H., "Boosting the Organizational Performance : Ethical Climate as a Moderator for Optimizing Risk Management Practices in the Saudi Public Sector", Global Business and Finance Review, 29(3), pp.42~56 (2024)[DOI]
  3. Adepu, N., "Analyzing the factors affecting construction project schedules amidst COVID-19 pandemic", Project Leadership and Society, 4 (2023)[DOI]
  4. Almohassen, A. S., "The effects of COVID-19 on safety practices in construction projects", Ain Shams Engineering Journal, 14(1), pp.101834~ (2022)[DOI]
  5. Balas, E. A., "A hybrid Monte Carlo simulation risk model for oil exploration projects", Marine Pollution Bulletin, 194 (2023)[DOI]
  6. Baloi, D., "Modelling global risk factors affecting construction cost performance", International Journal of Project Management, 21(4), pp.261~269 (2003)[DOI]
  7. Basak, M., "The interaction between non-technical and technical risks in upstream natural gas project schedule overruns : Evidence from Australia", Extractive Industries and Society, 8(4) (2021)[DOI]
  8. Basak, M., "Energy Reports (Vol. 5)", pp.210~220 (2019), Elsevier Ltd
  9. Boateng, P., "An Analytical Network Process model for risks prioritisation in megaprojects", International Journal of Project Management, 33(8), pp.1795~1811 (2015)[DOI]
  10. Carr, V., "A fuzzy approach to construction project risk assessment and analysis: construction project risk management system", Advances in Engineering Software, 32(10, pp.11) (2001), 847~857
  11. Chapman, R. J., "The controlling influences on efective risk identification and assessment for construction design management", International Journal of Project Management, 19, pp.147~160 (2001)[DOI]
  12. Cheng, C., "Risk measurement of international oil and gas projects based on the Value at Risk method", Petroleum Science, 16(1), pp.199~216 (2019)[DOI]
  13. Cheng, G. S., "The Identification and Management of Major Risks in the Malaysian Construction Industry", Journal of Construction in Developing Countries, 18(1), pp.19~32 (2013)
  14. Dehghan, R., "Quantitative Risk-Analysis Process of Oil and Gas Upstream Service Contracts", Practice Periodical on Structural Design and Construction, 27(2) (2022)[DOI]
  15. Dewan Energi Nasional, "Outlook Energi Indonesia 2019", ~ (2019)
  16. Dirjen Migas, "Statistik Minyak dan Gas Bumi Semester I 2022", ~ (2022)
  17. Ernst & Young, "Engineering Procurement &Construction (EPC) - Braving the headwinds", ~ (2013)
  18. Fallahnejad, M. H., "Delay causes in Iran gas pipeline projects", International Journal of Project Management, 31(1), pp.136~146 (2013)[DOI]
  19. Fan, M., "Choosing a project risk-handling strategy : An analytical model", International Journal of Production Economics, 112(2), pp.700~713 (2008)[DOI]
  20. Fang, C., "A simulation-based risk network model for decision support in project risk management", Decision Support Systems, 52(3), pp.635~644 (2012)[DOI]
  21. Filippin, K., "Major hazard risk assessment for existing and new facilities", Process Safety Progress, 23(4), pp.237~243 (2004)[DOI]
  22. Flyvbjerg, B., "Megaprojects and risk: an anatomy of ambition" (2003), Cambridge University Press
  23. Gierczak, M., "The quantitative risk assessment of MINI, MIDI and MAXI Horizontal Directional Drilling Projects applying Fuzzy Fault Tree Analysis", Tunnelling and Underground Space Technology, 43, pp.67~77 (2014)[DOI]
  24. Guan, Z., "Oil and gas drilling risk analysis utilizing quantitative risk assessment", Journal of Applied Science and Engineering, 21(4), pp.541~546 (2018)[DOI]
  25. Haghighi, M. H., "A new qualitative and quantitative analytical approach for risk management in energy project time-cost trade-off problem under interval type-2 fuzzy uncertainty : A case study in the gas industry", Energy Reports, 8, pp.12668~12685 (2022)[DOI]
  26. Han, S. H., "Analyzing schedule delay of mega project : Lessons learned from Korea train express", IEEE Transactions on Engineering Management, 56(2), pp.243~256 (2009)[DOI]
  27. Hatmoko, J. U. D., "Quantitative Risk Analysis for Oil and Gas Projects: A Case Study", IOP Conference Series: Earth and Environmental Science, 448(1) (2020)
  28. Hong, N. T. H., "T he E ffects o f Enterprise R isk Management on the Performance and Risk of Vietnamese Listed Firms : Evidence from Abnormal Enterprise Risk Management Index", Global Business and Finance Review, 28(5), pp.122~136 (2023)[DOI]
  29. Issa, U. H., "A model for evaluating the risk effects on construction project activities", Journal of Civil Engineering and Management, 25(7), pp.687~699 (2019)[DOI]
  30. Jang, W., "A stage-gate integrated risk control system for LNG plant projects : Focusing on the design phase", Journal of Natural Gas Science and Engineering, 22, pp.437~446 (2015)[DOI]
  31. Jergeas, G., "Improving Construction Productivity on Alberta Oil and Gas Capital Projects" (2009), Alberta Finance and Enterprise
  32. Kang, H. W., "Analysis of the probabilistic cost variation ranges according to the effect of core quantitative risk factors for an overseas plant project : Focused on a Middle East gas plant project", KSCE Journal of Civil Engineering, 20(2), pp.509~518 (2016)[DOI]
  33. Kassem, M., "Risk factors in oil and gas construction projects in developing countries : A case study", International Journal of Energy Sector Management, 13(4), pp.846~861 (2019)[DOI]
  34. Kazemi, A., "Identifying and prioritizing delay factors in Iran's oil construction projects", International Journal of Energy Sector Management, 15(3), pp.476~495 (2020)[DOI]
  35. Khadem, M. M. R. K., "Quantitative risk management in gas injection project : a case study from Oman oil and gas industry", Journal of Industrial Engineering International, 14(3), pp.637~654 (2018)[DOI]
  36. Khodeir, L. M., "Identifying the latest risk probabilities affecting construction projects in Egypt according to political and economic variables. From January 2011 to January 2013", HBRC Journal, 11(1), pp.129~135 (2015)[DOI]
  37. Kraidi, L., "Analyzing the critical risk factors associated with oil and gas pipeline projects in Iraq", International Journal of Critical Infrastructure Protection, 24, pp.14~22 (2019)[DOI]
  38. Kumar Gupta, V., "A quantitative risk assessment methodology for construction project", Indian Academy of Sciences, 43 (2018)[DOI]
  39. Mayer, J., "Qualitative and quantitative risk assessment of expanding photovoltaics in the Netherlands", Environmental Innovation and Societal Transitions, 35, pp.357~368 (2020)[DOI]
  40. Montgomery, D. C., "Design and analysis of experiments" (2013), John Wiley & Sons, Inc
  41. Nabawy, M., "A systematic review of quantitative risk analysis in construction of mega projects", Ain Shams Engineering Journal, 11(4), pp.1403~1410 (2020)[DOI]
  42. Nunnally, J., "Psychometric theory" (1994), McGraw-Hill, Inc
  43. Oh, K., "Effects o f Working Capital Management on Small and Mediu m-sized Enterprises' Profitability from the Continu ity of Su pply Chain Relationships", Global Business and Finance Review, 28(5), pp.51~66 (2023)[DOI]
  44. Orangi, A., "Exploring delays in Victoria-based Astralian pipeline projects", Procedia Engineering, 14, pp.874~881 (2011)[DOI]
  45. Perry, J., "Risk and its management in construction projects", Proceeding Institution Civil Engineers, 78(3), pp.499~521 (1985)
  46. Rawat, A., "A r eview on prospective risks and mitigation for oil and gas projects : implication for Indian CGD companies", International Journal of Energy Sector Management, 17(1), pp.41~62 (2023)[DOI]
  47. Ruqaishi, M., "Causes of Delay in Construction Projects in the Oil and Gas Industry in the Gulf Cooperation Council Countries : A Case Study", Journal of Management in Engineering, 31(3) (2015)[DOI]
  48. Srivastava, A., "New methodologies for security risk assessment of oil and gas industry", Process Safety and Environmental Protection, 88(6), pp.407~412 (2010)[DOI]
  49. Suslick, S. B., "Risk analysis applied to petroleum exploration and production : An overview", Journal of Petroleum Science and Engineering, 44(1-2), pp.1~9 (2004)[DOI]
  50. Sutalaksana, I. Z., "Teknik perancangan sistem kerja" (2006), Institut Teknologi Bandung
  51. Suvittawat, A., "Consumer adjustment spending habits due to the COVID-19 pandemic in Nakhon Ratchasima Province, Thailand", Environment and Social Psychology, 9(1) (2024)[DOI]
  52. Sweis, R., "Causes of delay in Iranian oil and gas projects : a root cause analysis", International Journal of Energy Sector Management, 13(3), pp.630~650 (2019)[DOI]
  53. Urgilés, P., "Methods for quantitative risks analysis of cost and deadline overruns in complex projects", Procedia Manufacturing, 41, pp.658~665 (2019)[DOI]
  54. Van Thuyet, N., "Risk management in oil and gas construction projects in Vietnam", International Journal of Energy Sector Management, 1(2), pp.175~194 (2007)[DOI]
  55. Vivek, A., "Identification and analysing of risk factors affecting cost of construction projects", Materials Today : Proceedings, 60, pp.1696~1701 (2022)
  56. Waqar, A., "Evaluating the critical safety factors causing accidents in downstream oil and gas construction projects in Malaysia", Ain Shams Engineering Journal, 15(1) (2023)[DOI]
  57. Westney, R., "Why projects overrun, and what to do about it" (2008), Westney Consulting Group
  58. "OTC 12979 Managing the Cost &Schedule Risk of Offshore Development Projects The Need for Project Risk Management" (2001)[URL]
  59. Whipple, T., "Applied risk-based process safety : A consolidated risk register and focus on risk communication", Process Safety Progress, 29(1), pp.39~46 (2010)[DOI]
  60. Yazdani-Chamzini, A., "Proposing a new methodology based on fuzzy logic for tunnelling risk assessment", Journal of Civil Engineering and Management, 20(1), pp.82~94 (2014)[DOI]

관련 논문AI추천

이 간행물의 다른 논문 (14건)