프로젝트 리스크 관리(PRM)가 프로젝트 성공에 미치는 효과성 분석: 해외건설사업 수행단계 전반을 중심으로
Analysis of the Effectiveness of Project Risk Management (PRM) on the Project Success: Focused on the Implementation Phase of Overseas Construction Projects
2
조회
0
다운로드
0
인용
0
참고문헌
키워드
초록
Under increased complexity and uncertainty of overseas construction projects, it is important for construction companies to improve their own project risk management capabilities instead of risk-taking strategies to secure competitiveness in the overseas construction market. Although most of the risks occur in project execution stage, many previous studies focused on planning stage including risk identification and analysis among PRM process. Therefore, this study aims to verify the effectiveness of whole PRM process during project execution stage through empirical study on participants of overseas construction projects. As the result it was found that first, the factor directly affects the project success is the execution process of PRM. It implies that appropriate actions such as appointing charged manager for risks, timely implementation of responding plan, continuous risk monitoring and updating established plan are the key for contribution to the project success. Second, the importance of communication in PRM is also found, which is not conducted at a specific but throughout the entire PRM process and need to be managed as essential factor for successful PRM..
Abstract
Under increased complexity and uncertainty of overseas construction projects, it is important for construction companies to improve their own project risk management capabilities instead of risk-taking strategies to secure competitiveness in the overseas construction market. Although most of the risks occur in project execution stage, many previous studies focused on planning stage including risk identification and analysis among PRM process. Therefore, this study aims to verify the effectiveness of whole PRM process during project execution stage through empirical study on participants of overseas construction projects. As the result it was found that first, the factor directly affects the project success is the execution process of PRM. It implies that appropriate actions such as appointing charged manager for risks, timely implementation of responding plan, continuous risk monitoring and updating established plan are the key for contribution to the project success. Second, the importance of communication in PRM is also found, which is not conducted at a specific but throughout the entire PRM process and need to be managed as essential factor for successful PRM..
참고문헌 (49)
- Akintoye, A. S., "Risk analysis and management in construction", International Journal of Project Management, 15(1), pp.31~38 (1997)
- Atkinson, R., "Project management: cost, time and quality, two best guesses and a phenomenon, it's time to accept other success criteria", International Journal of Project Management, 17(6), pp.337~342 (1999)
- Ayub, B., "Contingency release during project execution : The contractor’s deci-sion-making dilemma", Project Management Journal, 50(6), pp.734~748 (2019)
- Banaitiene, N, "Risk management : Current issues and challenges" (2012), BoD-Books on Demand
- Bannerman, P. L., "Risk and risk management in software projects : A reassessment", Journal of Systems and Software, 81(12), pp.2118~2133 (2008)
- Besner, C., "An empirical identification of project management toolsets and a comparison among project types", Project Management Journal, 43(5), pp.24~46 (2012)
- Carvalho, M. M. D., "Impact of risk management on project performance : the importance of soft skills", International Journal of Production Research, 53(2), pp.321~340 (2015)
- Cookie-Davies, T., "The real success factors on projects, International", Journal of Project Management, 20(3), pp.185~190 (2002)
- Crispim, J., "Project risk man-agement practices : The organizational maturity influence", Int. J. Manag. Proj. Bus, 12, pp.187~210 (2019)
- Fang, C., "A simulation-based risk network model for decision support in project risk management", Decision Support Systems, 3(52), pp.635~644 (2012)
- Guo, F., "Effects of project governance structures on the management of risks in major infrastructure projects : A comparative analysis", International Journal of Project Management, 32(5), pp.815~826 (2014)
- Hair, J. F., "PLS-SEM : Indeed a silver bullet", Journal of Marketing theory and Practice, 19(2), pp.139~152 (2011)
- Haniff, A. P., "Introduction to project management(The Global Management Series)" (2016), Goodfellow Publishers
- Henseler, J., "A new criterion for assessing discriminant validity in var-iance-based structural equation modeling", Journal of the Academy of Marketing Science, 43, pp.115~135 (2015)
- Hwang, B. G., "Risk management in small construction projects in Singapore: Status, bar-riers and impact", International Journal of Project Management, 32(1), pp.116~124 (2014)
- Ika, L. A., "Project success as a topic in project management journals", Project Management Journal, 40(4), pp.6~19 (2009)
- Ika, L. A., "The"re-meaning"of project success : Updating and recalibrating for a modern project management", International Journal of Project Manage-ment, 40(7), pp.835~848 (2022)
- Statistics for overseas construction contract re-ceivables, Statistical Information Report, "ICAK", ~ (2022)
- "ICB 4.0, IPMA", ~ (2015)
- "ISO 21500:2012", ISO, ~ (2012)
- Jugdev, K., "A retrospective look at our evolving understanding of project success", Project Management Journal, 36(4), pp.19~31 (2005)
- Batagalle Vinuri Gimanthika Karunarathne, "Risk Management Application-Level Analysis in South Korea Construction Companies Using a Generic Risk Maturity Model", KSCE Journal of Civil Engineering, 25(9), pp.3235~3244 (2021), 대한토목학회[DOI]
- Lee, G. P., "Diagnosis of overseas project management capabilities of domestic construction com-panies, Construction and Economy Research Institute of Korea", Construction Issue Focus, 10, pp.1~33 (2018)
- Ling, F. Y. Y., "Key project management practices affecting Singaporean firms’ project performance in China", International Journal of Project Management, 27(1), pp.59~71 (2009)
- Low, S. P., "Environmental factors and work performance of project managers", International Journal of Project Management, 21(1), pp.24~37 (2006)
- Lyons, T., "Project risk management in the Queensland engineering construction industry : a survey", International Journal of Project Management, 22(1), pp.51~61 (2004)
- Abteen Ijadi Maghsoodi, "Identification and Evaluation of Construction Projects' Critical Success Factors Employing Fuzzy-TOPSIS approach", KSCE Journal of Civil Engineering, 22(5), pp.1593~1605 (2018), 대한토목학회[DOI]
- Mashwama, X. N., "Investigation of construction stakeholders’ perception on the effects & cost of construction dispute in Swaziland", Procedia Engineering, 164, pp.196~205 (2016)
- Memon, A. H., "Time overrun in construction projects from the per-spective of project management consultant (PMC)", Journal of Surveying, Construction and Property, 2(1), pp.54~66 (2011)
- Oehmen, J., "Analysis of the effect of risk management practices on the performance of new product development pro-grams", Technovation, 34(8), pp.441~453 (2014)
- Osipova, E., "Risk management in the different phases of a construction project: a study of actors' involvement", Nordic Conference on Construction Economics and Organsiation, pp.307~319 (2007), Luleå tekniska universitet
- "PMBOK Guide", PMI, ~ (2017)
- "PRINCE2, OGC", ~ (2017)
- Rabechini Junior, R., "Understanding the impact of project risk management on project performance: An empirical study", Journal of Technology Management & Innovation, 8(6) (2013)
- Raz, T., "Risk management, project success, and technological uncertainty", R&d Management, 32(2), pp.101~109 (2002)
- Retfalvi, A. L., "The benefits of event-based Risk Management in project execution", PMI Global Congress (2009)
- Ritchie, J., "Qualitative research practice : A guide for social science students and researchers" (2013), sage
- Royer, P. S., "Risk management : The undiscovered di-mension of project management", Project Management Journal, 31(1), pp.6~13 (2000)
- Shayan, S., "Critical success factor analysis for effective risk management at the execution stage of a construction project", International Journal of Construction Management, 22(3), pp.379~386 (2022)
- Shenhar, A. J., "Reinventing project manage-ment, The diamond approach to successful growth and innovations" (2007), Harvard Business School Press
- Siddiqui, S. Q., "Six Sigma in construction : a review of critical success factors", International Journal of Lean Six Sigma, 7(2), pp.171~186 (2016)
- Tavares, B. G., "Practices to improve risk management in agile projects", International Journal of Software Engineering and Knowledge Engineering, 29(3), pp.381~399 (2019)
- Teller, J., "An empirical investigation on how portfolio risk management influences project portfo-lio success", International Journal of Project Manage-ment, 31(6), pp.817~829 (2013)
- Willumsen, P., "Value creation through project risk management", International Journal of Project Management, 37(5), pp.731~749 (2019)
- Wood, D., "Project execution risk management for addressing construct-ability: Use construction knowledge, experience and effi-ciency in a structured and systematic way throughout the design and execution planning stages: Plant design and engineering", Hydrocarbon processing (International ed.), 87(12), pp.35~42 (2008)
- Xia, N., "Towards integrating construction risk management and stakeholder management : A systematic literature re-view and future research agendas", International Journal of Project Management, 36(5), pp.701~715 (2018)
- Zavadskas, E. K., "Risk assessment of construction projects", Journal of Civil Engineering and Management, 16(1), pp.33~46 (2010)
- Zhi, H., "Risk management for overseas construction proj-ects", International Journal of Project Management, 13(4), pp.231~237 (1995)
- Zwikael, O., "The effectiveness of risk man-agement : an analysis of project risk planning across in-dustries and countries", Risk Analysis : An International Journal, 31(1), pp.25~37 (2011)