Optimization of long-term planning with a constraint satisfaction problem algorithm with a machine learning
1
조회
0
다운로드
3
인용
0
참고문헌
키워드
초록
The object of the long-term planning in shipyards is to assign the ordered vessels to the berths with the consideration of the workload balancing. However, there are limitations in establishing an optimized long-term plan because the workload balancing takes too much time due to the size and the complexity of the problem domain. Most shipyards currently overcome the limitations by dividing the long-term planning into two-phase of the berth planning and the capacity planning. The berth planning is being conducted with a heuristic method by considering some rules such as the berth priority and the closeness to delivery date. Then it is followed by the capacity planning, in which the workload data is considered for the workload balancing with the previously planned data. However, the heuristic method has a fundamental problems that the optimized solution is not guaranteed owing to the limits of the search range. Also, the previous production record cannot reflect the newly ordered vessel's workload precisely. In this study, a constraint satisfaction technique is used for the optimization of the berth planning. In addition, the workload prediction model is developed based on the supervised learning with a deep neural network. Finally, proposed methods are tested with the shipyard actual data, that shows the improved results.
Abstract
The object of the long-term planning in shipyards is to assign the ordered vessels to the berths with the consideration of the workload balancing. However, there are limitations in establishing an optimized long-term plan because the workload balancing takes too much time due to the size and the complexity of the problem domain. Most shipyards currently overcome the limitations by dividing the long-term planning into two-phase of the berth planning and the capacity planning. The berth planning is being conducted with a heuristic method by considering some rules such as the berth priority and the closeness to delivery date. Then it is followed by the capacity planning, in which the workload data is considered for the workload balancing with the previously planned data. However, the heuristic method has a fundamental problems that the optimized solution is not guaranteed owing to the limits of the search range. Also, the previous production record cannot reflect the newly ordered vessel's workload precisely. In this study, a constraint satisfaction technique is used for the optimization of the berth planning. In addition, the workload prediction model is developed based on the supervised learning with a deep neural network. Finally, proposed methods are tested with the shipyard actual data, that shows the improved results.
참고문헌 (19)
- Chao, L. -C., "Estimating project S-curves using polynomial function and neural networks", J. Construct. Eng. Manag, 135(3), pp.169~177 (2009)
- Comparing the Productivity of Major Shipyards in China, South Korea, and Japanean Application of a Metafrontier Framework, "Chao, S. -L.", Maritime Business Review, ~ (2020)
- Hudson, K., "DHSS expenditure forecasting method", Chartered SurveyoreBuilding and Quantity Surveying Quarterly, 5, pp.42~45 (1978)
- Ju, S., "Integration of long-term planning and mid-term scheduling of shipbuilding", Prod. Plann. Control, pp.1~19 (2021)
- Kim, H., "A model for a simulation-based shipbuilding system in a shipyard manufacturing process", Int. J. Comput. Integrated Manuf, 18(6), pp.427~441 (2005)
- 김연민, "조선 성과 측정을 위한 다차원 생산성의 분석", 경영과학, 34(2), pp.57~66 (2017), 한국경영과학회[DOI]
- Koh, S., "Spatial scheduling for shape-changing mega-blocks in a shipbuilding company", Int. J. Prod. Res, 49(23), pp.7135~7149 (2011)
- Lee, J. M., "Development of an evaluation framework of production planning for the shipbuilding industry", Int. J. Comput. Integrated Manuf, 31(9), pp.831~847 (2018)
- Lu, W., "The S-curve for forecasting waste generation in construction projects", Waste Manag, 56, pp.23~34 (2016)
- SeungHoon Nam, "SCP-Matrix based shipyard APS design: Application to long-term production plan", International Journal of Naval Architecture and Ocean Engineering, 10(6), pp.741~761 (2018), 대한조선학회
- Okumoto, Y., "Optimization of block erection using a genetic algorithm", J. Ship Prod, 18(2), pp.116~119 (2002)
- Park, J. -C., "A study on the application of Scurve for basic plan in a shipbuilding yard", IE interfaces, 7(3), pp.201~212 (1994)
- 박석호, "조선산업의 생산성과 효율성 변화와 그 결정요인", 한국항만경제학회지, 28(2), pp.155~177 (2012), 한국항만경제학회[DOI]
- San Cristobal, J., "The S-curve envelope as a tool for monitoring and control of projects", Procedia Comput. Sci, 121, pp.756~761 (2017)
- Skitmore, M., "Parameter prediction for cash flow forecasting models", Construct. Manag. Econ, 10(5), pp.397~413 (1992)
- Snoek, J., "Practical bayesian optimization of machine learning algorithms", Adv. Neural Inf. Process. Syst, pp.25~ (2012)
- 송영주, "시뮬레이션을 이용한 블록조립 공정 능력 분석", 대한조선학회 논문집, 46(1), pp.78~86 (2009), 대한조선학회
- Tang, W., "A ship berthing model with uncertain factors for shipyards", The Twenty-Fourth International Ocean and Polar Engineering Conference (2014)
- Woo, J. H., "Development of simulation framework for shipbuilding", Int. J. Comput. Integrated Manuf, 31(2), pp.210~227 (2018)
