FPSO의 선행의장률 향상을 위한 생산관리 및 공법개선 사례연구
Process Improvements for Elevating Pre-outfitting Rate of FPSO
2
조회
0
다운로드
2
인용
0
참고문헌
키워드
초록
Generally, functional design of FPSO has been done by the engineering firm designated by ship owner. Main equipment such as topside facility isimported from abroad. But sometimes, OFE (Owner Furnished Equipment) does not satisfy the PND (Product Need Date) of each production stage because the delivery date of OFE is not scheduled to satisfy the PND. And sometimes many loose items and equipment are complex from engineering which does not consider pre-outfitting. Main objective of this study is process improvements by maximizing pre-outfitting rate in the stage of equipping STP (Submerged Turret Production), one of main equipment on FPSO. In this study, we analyzed the factors which obstructed pre-equipping STP using the past records of FPSO projects.
Abstract
Generally, functional design of FPSO has been done by the engineering firm designated by ship owner. Main equipment such as topside facility isimported from abroad. But sometimes, OFE (Owner Furnished Equipment) does not satisfy the PND (Product Need Date) of each production stage because the delivery date of OFE is not scheduled to satisfy the PND. And sometimes many loose items and equipment are complex from engineering which does not consider pre-outfitting. Main objective of this study is process improvements by maximizing pre-outfitting rate in the stage of equipping STP (Submerged Turret Production), one of main equipment on FPSO. In this study, we analyzed the factors which obstructed pre-equipping STP using the past records of FPSO projects.
참고문헌 (6)
- Bae M.H., "The Optimum Design of Green Water Protector for FPSO, Special Issue of the Society of Naval Architect of Korea", pp.94~98 (2007)
- Lee J.W., "Erection Process Planning & Scheduling using Genetic Algorithm", Transactions of the Society of Naval Architecture of Korea, 32(1), pp.9~16 (1995)
- Min S.G., "A Case Study for Development of the Block Arrangement on Fixed Area and Scheduling System , Special Issue of the Society of Naval Architect of Korea", pp.159~164 (2005)
- Park J.H., "The Current Situation and Development Direction about FPSO", Journal of the Society of Naval Architects of Korea, 44(2), pp.43~50 (2007)
- Sim W.S., "Fatigue design practice in shortened project schedule", Journal of the Society of Naval Architects of Korea, Proceedings of the Annual Autumn Meeting The Society of Naval Architects of Korea, pp.902~907 (2004)
- Son H.J., "Offshore Engineering" (2007), Sunhack publishing company