조선 전용 GIS와 안벽 시뮬레이터를 이용한 후행 중일정 최적화

An Optimization of Process Planning around Quays based on the Yard Customized GIS and the Simulator

2

조회

0

다운로드

4

인용

0

참고문헌

키워드

주제분류조선공학

초록

This paper has focused on the middle term process planning around quays based on the prefixed long-term plan of the product mixedships. Recently, the order rate of high add-value ships in domestic shipyards has been sharply increased and the spending time atquays is accordingly on an increasing trend. For proper and practical process planning related to quays, it has to be closely connectedwith a long-term plan and product calendar, erection network and result of ship allocation around quays. Moreover, it is also requiredto include the integrated consideration of the whole process of a yard, each ship, and each team respectively. The most distinguishingfeature of this study is that it would run on the ship allocation simulator and GIS framework in order not to be limited to the specific oneyard and the readers can figure out the optimization formulation containing the work load leveling and a different approach fromPERT/CPM. The proposed approach reflected all requirements from the department of process planning and management in a shipyard,and the analysis of the results has explained its performance of the optimization result with the examples of total 43 ships underconstruction from 2008 to 2013.

Abstract

This paper has focused on the middle term process planning around quays based on the prefixed long-term plan of the product mixedships. Recently, the order rate of high add-value ships in domestic shipyards has been sharply increased and the spending time atquays is accordingly on an increasing trend. For proper and practical process planning related to quays, it has to be closely connectedwith a long-term plan and product calendar, erection network and result of ship allocation around quays. Moreover, it is also requiredto include the integrated consideration of the whole process of a yard, each ship, and each team respectively. The most distinguishingfeature of this study is that it would run on the ship allocation simulator and GIS framework in order not to be limited to the specific oneyard and the readers can figure out the optimization formulation containing the work load leveling and a different approach fromPERT/CPM. The proposed approach reflected all requirements from the department of process planning and management in a shipyard,and the analysis of the results has explained its performance of the optimization result with the examples of total 43 ships underconstruction from 2008 to 2013.

참고문헌 (10)

  1. Choi, H.S., "Simulation based on GIS", Special Issue of the Society of Naval Architects of Korea, 48(4), pp.18~23 (2011)
  2. Hong, S. I., "Algorithm for the Quay Assignment Scheduling Problem in Shipbuilding Industry", pp.2008
  3. Javanshir, H., "Optimal Allocation of Ships to Quay Length in Container Ports", Journal of Industrial and Systems Engineering, 3(4), pp.275~290 (2010)
  4. Jeong, S. B., "A Study on the Quay Planning in shipbuilding industry", Proceedings of the Annual Korean Association of Industrial Business Administration, pp.248~259 (2012)
  5. Kim, O. S., "Shipbuilding Technology & Production System" (2012), GS Intervision Press
  6. Kirkpatrick, S., "Optimization by Simulated Annealing", Science, 220(4598), pp.671~680 (1983)
  7. Lee, G.H., "A study on CCPM technology in shipbuilding industry", Proceedings of the Annual Korean Association of Industrial Business Administration, pp.248~259 (2012)
  8. Study on the Positioning System for Logistics of Ship-block, "Lee, Y.H.", Special Issue of the Society of Naval Architects of Korea, 68~75 (2008)
  9. Park, K. S., "Heuristic Algorithms for Resource Leveling in Outfitting Scheduling of Shipbuilding", pp.2003
  10. Ruy, W.S., "Optimization of Outdoor planning using Quay Simulator", Proceedings of the Annual KAOST, pp.442~445 (2012)