해양 공사 EPC 견적용 중량 추산 방법에 관한기초 연구
A Preliminary Study on a Method for the Weight Estimation and Calculation of Offshore EPC Projects
0
조회
0
다운로드
1
인용
0
참고문헌
키워드
초록
There are several existing studies for the weight estimation of offshore plants. However, most of them were applicable at the pre-FEED (Front End Engineering Design) stage. In this paper, a preliminary study on a method for the weight estimation and calculation of offshore EPC (Engineering Procurement Construction) projects is made for the use at the estimation stage after FEED. Based on literature surveys including ISO (International Organization for Standardization) 19901-5 about weight estimation, we proposes new weight factors and a weight curve. Weight factors defined in this study include MTO (Material Take-Off), estimated weight, FEED maturity factor, allowance factor, and contingency factor. The proposed method utilizes bottom-up approach for weight estimation and it can be used for the weight estimation and calculation of offshore EPC projects at the estimation stage.
Abstract
There are several existing studies for the weight estimation of offshore plants. However, most of them were applicable at the pre-FEED (Front End Engineering Design) stage. In this paper, a preliminary study on a method for the weight estimation and calculation of offshore EPC (Engineering Procurement Construction) projects is made for the use at the estimation stage after FEED. Based on literature surveys including ISO (International Organization for Standardization) 19901-5 about weight estimation, we proposes new weight factors and a weight curve. Weight factors defined in this study include MTO (Material Take-Off), estimated weight, FEED maturity factor, allowance factor, and contingency factor. The proposed method utilizes bottom-up approach for weight estimation and it can be used for the weight estimation and calculation of offshore EPC projects at the estimation stage.
참고문헌 (19)
- Bjerkelund, T., "Weight Margins and Flexibility in Offshore Rigs", M.Sc., pp.2013
- Bolding, A., "Bulk Factor Method Estimates FPSO Topsides Weight", Oil & Gas Journal, 99(10), pp.49~52 (2001)
- 조용진, "통계적 접근법에 의한 선박 중량추정 방법 개발", 대한조선학회 논문집, 48(5), pp.426~434 (2011), 대한조선학회
- "Cleopatra Enterprise, Weight Management and Philosophy" (2015)[URL]
- Hall, N.A., "Cost estimation challenges and uncertainties confronting oil and gas companies, AACE International Transactions, EST. 491", AACE International Annual Meeting, Atlanta, United State of America (2011)
- AB-GCP Topsides Weight Control Report, "Iranian Offshore Oil Company", IOOC, ~ (2006)
- Petroleum and natural gas industries - Specific requirements for offshore structure - Part 5: Weight control during engineering and construction, "International Organization for Standardization", ISO, ~, pp.ISO Report 19901-5 (2003)
- Lee, S. H., "Technical strategic on the EPC risk for offshore plant", The Korean Association of Ocean Science and Technology Societies conference (2015)
- Mohamed A. E., "Offshore Structures Design, Construction and Maintenance" (2012), Gulf Professional Publishing
- Cost Engineering for Plant EPC Project, Technical Course, "POSTECH", ~ (2015)
- "Ramboll Oil & Gas" (2015)[URL]
- Rui, R., "Upstream Offshore-Facility Weight-Growth Study", Oil and Gas Facilities, 4(2), pp.107~112 (2015)
- Society of Allied Weight Engineers, "Weight Estimating Margin Manual for Marine Vehicles", SAWE, Standards and Practices, ~ (2001)
- 서성호, "통계적 방법을 이용한 부유식 해양 플랜트의 중량 추정용 간이 모델 연구", 대한조선학회 논문집, 50(6), pp.373~382 (2013), 대한조선학회
- 서성호, "비선형 회귀 분석을 이용한 부유식 해양 구조물의중량 추정 모델 연구", 대한조선학회 논문집, 51(6), pp.530~538 (2014), 대한조선학회
- Shetelig, H., "Shipbuilding Cost Estimation-Parametric Approach", M.Sc., pp.2013
- "ShipWeight" (2015)[URL]
- 엄태섭, "유전적 프로그래밍 방법을 이용한 부유식 해양 구조물의 중량 추정 모델", 한국CDE학회 논문집, 19(1), pp.1~11 (2014), 한국CDE학회[DOI]
- 엄태섭, "개선된 유전적 프로그래밍 방법을 이용한 부유식 해양 구조물의 중량 추정 모델 연구", 대한조선학회 논문집, 52(1), pp.1~7 (2015), 대한조선학회