The extensible supply of New & Renewable energy resources desperately needs to counter the high dependence on imported energy, recent high oil prices and the Climate Change Conference, and the government has operated the ‘Renewable Portfolio Standard’ (RPS) as one of the renewable energy policy from 2012. By analyzing the operation case of combined heat and power plant using the woodchip biomass, we drew the price of wood chip fuel, plant capacity factor, electricity selling price,heat selling price and LCOE value. After analyzing the economic feasibility of 3MWe combined heat and power plant based on the operating performance, the minimum of economic feasibility has appeared to be secured according to the internal rate of return (IRR) is 6.34% and the net present value (NPV) is 3.6 billion won as of 20 years life time after installation, and after analyzing the cases of the economic feasibility of the price of wood chip, plant capacity factor, electricity and heat selling price are changed, the economic feasibility is valuable when the price of wood chip is over 64,000 won/ton, NPV is minus, and the capacity factor is above 46.9%, the electricity selling price is 116 won/kWh and the heat selling price is above 75,600 won/Gcal. When going over the new installation hereafter, we need the detailed review of the woodchip storage and woodchip feeding system rather than the steam-turbine and boiler which have been inspected many times, the reason why is it’s hard to secure the suitable quality (constant size) of woodchip by the lack of understanding about it as a fuel because of the domestic poor condition and the calorific value of woodchip is seriously volatile compared with other fuels.
Abstract
The extensible supply of New & Renewable energy resources desperately needs to counter the high dependence on imported energy, recent high oil prices and the Climate Change Conference, and the government has operated the ‘Renewable Portfolio Standard’ (RPS) as one of the renewable energy policy from 2012. By analyzing the operation case of combined heat and power plant using the woodchip biomass, we drew the price of wood chip fuel, plant capacity factor, electricity selling price,heat selling price and LCOE value. After analyzing the economic feasibility of 3MWe combined heat and power plant based on the operating performance, the minimum of economic feasibility has appeared to be secured according to the internal rate of return (IRR) is 6.34% and the net present value (NPV) is 3.6 billion won as of 20 years life time after installation, and after analyzing the cases of the economic feasibility of the price of wood chip, plant capacity factor, electricity and heat selling price are changed, the economic feasibility is valuable when the price of wood chip is over 64,000 won/ton, NPV is minus, and the capacity factor is above 46.9%, the electricity selling price is 116 won/kWh and the heat selling price is above 75,600 won/Gcal. When going over the new installation hereafter, we need the detailed review of the woodchip storage and woodchip feeding system rather than the steam-turbine and boiler which have been inspected many times, the reason why is it’s hard to secure the suitable quality (constant size) of woodchip by the lack of understanding about it as a fuel because of the domestic poor condition and the calorific value of woodchip is seriously volatile compared with other fuels.
참고문헌 (8)
- 지식경제부, "에너지통계연보", ~ (2011)
- "신・재생에너지 공급 의무화제도 관리 및 운영지침", 지경부 고시 제2012-134호, ~ (2012)
- 폐목재 관리체계 개선 및 재활용 활성화방안 연구, "국립환경과학원", ~ (2007)
- 신재생 바이오에너지시설 타당성 검토 보고서, "KDHC", ~ (2006)
- 우드칩 조달방법, 체계 및 품질규격 최적화 개선 연구 최종보고서, "KDHC", ~ (2011)
- KDHC, "운영실적 자료(2010. 1~2012. 5)", ~ (2012)
- Thumann, Albert, "Handbook of Financing Energy Projects", ~ (2005)
- BlueNext Spot CER since 12, "08", 2008, pp.2012, ~