Cost-effectiveness of Tunnel Blasting Pattern by Applying Large Blasting Holes

0

조회

0

다운로드

0

인용

0

참고문헌

키워드

초록

The research is carried out to analyze the cost-effectiveness of blasting patterns with regard to the diameters and design of blasting holes. Blasting patterns for single diameter array, and mixed diameter array were comparatively analyzed with regard to drilling and charging time, and materials required. The number of blasting holes required for single array pattern and mixed array pattern were 138 and 93 holes, respectively. From the drilling time analysis, reduction in time and its efficiency of mixed pattern were 139 minutes and 25%, respectively, in comparison with single pattern. Charging time reduction and its efficiency of mixed blasting pattern were evaluated as 22.5 minutes per worker and 33%, respectively, compare to single blasting pattern. The explosive quantities of G1 and G2 required for single array patterns were 270 and 30, while those were 222 and 20 for mixed array patterns for tunnelling 4m. And single pattern required 45 more detonators than the mixed pattern. The evaluation of material required can also be positive parameter for cost reduction of tunnel construction.

Abstract

The research is carried out to analyze the cost-effectiveness of blasting patterns with regard to the diameters and design of blasting holes. Blasting patterns for single diameter array, and mixed diameter array were comparatively analyzed with regard to drilling and charging time, and materials required. The number of blasting holes required for single array pattern and mixed array pattern were 138 and 93 holes, respectively. From the drilling time analysis, reduction in time and its efficiency of mixed pattern were 139 minutes and 25%, respectively, in comparison with single pattern. Charging time reduction and its efficiency of mixed blasting pattern were evaluated as 22.5 minutes per worker and 33%, respectively, compare to single blasting pattern. The explosive quantities of G1 and G2 required for single array patterns were 270 and 30, while those were 222 and 20 for mixed array patterns for tunnelling 4m. And single pattern required 45 more detonators than the mixed pattern. The evaluation of material required can also be positive parameter for cost reduction of tunnel construction.

참고문헌 (12)

  1. "Drilling and blasting as a tunnel excavation method" (2000)[URL]
  2. "Optimization of blasting parameters in opencast mines" (2007)[URL]
  3. B. H. Chung, "Patent No. 10-1400797", Korean Intellectual Property Office, ~ (2014)
  4. WallTech, "Patent No. 10-1999-0037866", Korean Intellectual Property Office, ~ (1999)
  5. Y. Q. Yu, "Physical scale modelling of roadway advance with wedge cut blasting for South Wing rail at Tunliu mine", 2012Coal Operators’ Conference, pp.169~174 (2012), The University of Wollongong
  6. P. K. Singh, "Rock fragmentation control in opencast blasting", Journal of Rock Mechanics and Geotechnical Engineering, 8(2), pp.225~237 (2016)[DOI]
  7. S. S. Kim, "Patent No. 10-1551905", Korean Intellectual Property Office, ~ (2015)
  8. The report of ground survey-underground western arterial road construction plan, "West-Seoul Beltway LTD", West-Seoul Beltway LTD, ~ (2015)
  9. The Report of Western Arterial Road Construction Plan, "Samho C&M", Samho Development, ~ (2017)
  10. D. S. Shim, "U S Patent No US 20010025583A1", U. S. Patent and Trademark Office, ~ (2001)
  11. C. W. Lee, "Full-scale tests for assessing blasting-induced vibration and noise", Journal of Shock and Vibration, 10, pp.1~14 (2018)[DOI]

관련 논문AI추천

이 간행물의 다른 논문 (29건)