국내 표준품셈 현황 조사 및 원전해체 표준품셈 제정에 관한 고찰

A Study on the Current Status of Korean Standard Cost Estimates and the Establishment of Standard Cost Estimate for Nuclear Decommissioning

0

조회

0

다운로드

2

인용

0

참고문헌

키워드

초록

Recently, interest in the decommissioning of nuclear power plants is increasing due tothe permanent shutdown of commercial nuclear power plants such as Wolsong Unit 1 and Kori unit1. Since there is no experience in decommissioning commercial nuclear power plants in Korea, manypending issues such as development of technology and decommissioning regulations are piled up. Among them, pending issues such as waste management measures, and evaluation of decommissioningcosts are classified as issues that must be urgently resolved before decommissioning proceeds. Inparticular, continuous research is required to estimate the cost of decommissioning nuclear powerplants in accordance with the social, institutional, and technical requirements. Therefore, this studyinvestigated the standard cost estimates system in other fields among the domestic construction costcalculation systems. Through this, we investigated and analyzed how the current nuclear power plantdecommissioning cost evaluation is being carried out, and suggested the direction for enacting thestandard cost estimate system for nuclear power plant decommissioning. The direction of enactmentof standard cost estimate system for nuclear power plant decommissioning suggested through thisstudy can be used to introduce standard cost estimate system for nuclear power plant decommissioningbusiness. In addition, it is expected that it can contribute to cost reduction and proper estimation ofexpected cost of nuclear power plant decommissioning in the future.

Abstract

Recently, interest in the decommissioning of nuclear power plants is increasing due tothe permanent shutdown of commercial nuclear power plants such as Wolsong Unit 1 and Kori unit1. Since there is no experience in decommissioning commercial nuclear power plants in Korea, manypending issues such as development of technology and decommissioning regulations are piled up. Among them, pending issues such as waste management measures, and evaluation of decommissioningcosts are classified as issues that must be urgently resolved before decommissioning proceeds. Inparticular, continuous research is required to estimate the cost of decommissioning nuclear powerplants in accordance with the social, institutional, and technical requirements. Therefore, this studyinvestigated the standard cost estimates system in other fields among the domestic construction costcalculation systems. Through this, we investigated and analyzed how the current nuclear power plantdecommissioning cost evaluation is being carried out, and suggested the direction for enacting thestandard cost estimate system for nuclear power plant decommissioning. The direction of enactmentof standard cost estimate system for nuclear power plant decommissioning suggested through thisstudy can be used to introduce standard cost estimate system for nuclear power plant decommissioningbusiness. In addition, it is expected that it can contribute to cost reduction and proper estimation ofexpected cost of nuclear power plant decommissioning in the future.

참고문헌 (11)

  1. Gang S-H, "Development of methodology for cost evaluation of nuclear power plant decommissioning", 2009 Proceedings of the Korean Radioative Waste Society Conference, 7(2), pp.33~34 (2009)
  2. "The scale of the decommissioning cost estimate of nuclear power plants varies widely" (2017)[URL]
  3. "In six years, 200 billion won has risen... Calculation of the cost of decommissioning Kori Unit 1 by rule of thumb?" (2020)[URL]
  4. "6500 → 7500 → 850 billion… Nuclear decommissioning cost snowball" (2020)[URL]
  5. Nuclear Safety and Security Commission, "Regulations on the Preparation of Plans for Decommissioning NPPs" (2022)
  6. Ministry of Land, Infrastructure and Transport, "Management Regulations of the Cost of Performed Construction and Standard Costing Management Regulations", pp.2008~2078 (2008)
  7. Korea Institute of Civil Engineering and Building Technology, "2022 Standard Costing of Construction", ~ (2022)
  8. 김재현, "국내 표준품셈 품의 할증을 활용한 국내 원자력발전소 해체 작업난이도 인자 개선 방안 연구", 방사선산업학회지, 16(1), pp.63~68 (2022), (사)한국방사선산업학회[DOI]
  9. Korean Mech. Const. Contrators Associtaion, "Mechanical Facilities", Establishment and revision procedures, and public announcement for standard costing of construction, 299, pp.87~93 (2015)
  10. Korea Mechanical Construction Contractors Association, "2021 Standard Costing Manual of Information & Communication Contractors" (2020)
  11. Kim HG, "Status and plan of development of decommissioning nuclear power plant dismantling technology", Nucl. Ind, 34(3), pp.33~35 (2014)

이 간행물의 다른 논문 (12건)