Analysis of Working Time at the Test Site of Southwest Offshore Wind Project in Korea Based on Weather Window

1

조회

0

다운로드

1

인용

0

참고문헌

키워드

주제분류토목공학

초록

As a preparation process for successful establishment of demonstration offshore wind farm, analyses have been made for working time at the construction site where working time is defined as the time available for marine operation to take place under given weather conditions. Data used are hourly wave and wind data from met mast, HeMOSU-1, and 3 hour numerical model data from Korea Meteorological Administration (KMA). Seasonal results show the minimum working time during winter and moderate during autumn and spring. The most working time was seen during summer on average. Monthly analyses show the most working time in May, June, and August which was higher than the working time in July and September. Working time reaches at steady state and no significant change was seen above wave height of 1.5 m and wind speed of 8 m/s.

Abstract

As a preparation process for successful establishment of demonstration offshore wind farm, analyses have been made for working time at the construction site where working time is defined as the time available for marine operation to take place under given weather conditions. Data used are hourly wave and wind data from met mast, HeMOSU-1, and 3 hour numerical model data from Korea Meteorological Administration (KMA). Seasonal results show the minimum working time during winter and moderate during autumn and spring. The most working time was seen during summer on average. Monthly analyses show the most working time in May, June, and August which was higher than the working time in July and September. Working time reaches at steady state and no significant change was seen above wave height of 1.5 m and wind speed of 8 m/s.

참고문헌 (5)

  1. Braam, H., "Assessment of wind and wave data measured at IJmuiden Munitiestortplaats", “Operation and Maintenance” consortium, ~ (2005)
  2. Jung, W. M., "Analysis of the wave-induced downtime for Pohang New Harbor", Journal of Korean Society of Coastal and Ocean Engineers, 9(1), pp.24~34 (1997)
  3. Analysis on Offshore Working Time of Demonstration Offshore Wind Farm in the Southern Part of West Sea, "Kim, J. K.", Korea Wind Energy Association, ~ (2012)
  4. O&M aspects of the 500MW offshore wind farm at NL7, , DOWEC, ~ (2002)
  5. "Regulations on industrial safety standards", Ministry of Labor, ~ (2006)