휴리스틱 기법을 이용한 포병진지 구축작전시 공병장비 최적배정
Optimal Allocation Heuristic Method of Military Engineering Equipments during Artillery Position Construction Operation
0
조회
0
다운로드
5
인용
0
참고문헌
키워드
초록
Artillery fire power due to effectiveness which is hard to predict well-planned and surprising attack can give a fear and shock to the personnel and is a very core weapon system and takes a critical role in wartime. Therefore in order to maximize operational effectiveness, Army required protecting artillery and takes a quick attack action through rapid construction of artillery’s positions. The artillery use artillery’s position to prevent exposure by moving to other position frequently. They have to move and construct at new artillery’s positions quickly against exposing existed place by foe’s recognition. These positions should be built by not manpower but engineering construction equipment. Because artillery positions have to protect human and artillery equipment well and build quickly. Military engineering battalion have lots of construction equipment which include excavator, loader, dozer, combat multi-purposed excavator, armored combat earthmover dump truck and so on. So they have to decide to optimal number of Team combining these equipments and determine construction sequence of artillery’s position in operational plan. In this research, we propose to decide number of Team efficiently and allocate required construction’s positions for each Team under constraints of limited equipments and time. To do so, we develop efficient heuristic method which can give near optimal solution and be applied to various situation including commander’s intention, artillery position’s priority or grouping etc. This heuristic can support quick and flexible construction plan of artillery positions not only for using various composition’s equipment to organize Teams but also for changing quantity of positions.
Abstract
Artillery fire power due to effectiveness which is hard to predict well-planned and surprising attack can give a fear and shock to the personnel and is a very core weapon system and takes a critical role in wartime. Therefore in order to maximize operational effectiveness, Army required protecting artillery and takes a quick attack action through rapid construction of artillery’s positions. The artillery use artillery’s position to prevent exposure by moving to other position frequently. They have to move and construct at new artillery’s positions quickly against exposing existed place by foe’s recognition. These positions should be built by not manpower but engineering construction equipment. Because artillery positions have to protect human and artillery equipment well and build quickly. Military engineering battalion have lots of construction equipment which include excavator, loader, dozer, combat multi-purposed excavator, armored combat earthmover dump truck and so on. So they have to decide to optimal number of Team combining these equipments and determine construction sequence of artillery’s position in operational plan. In this research, we propose to decide number of Team efficiently and allocate required construction’s positions for each Team under constraints of limited equipments and time. To do so, we develop efficient heuristic method which can give near optimal solution and be applied to various situation including commander’s intention, artillery position’s priority or grouping etc. This heuristic can support quick and flexible construction plan of artillery positions not only for using various composition’s equipment to organize Teams but also for changing quantity of positions.
참고문헌 (14)
- Choi, J. H., "Factors Affecting Selection and Combination of Earthwork Equipment", Korea Journal of Construction Engineering and Management, 10(1), pp.201~205 (2010)
- Dileep, R. S., "Industrial Scheduling" (1997), PWS Publishing Company
- Hong, S. P., "Management Science" (2010), Yul-Gok
- Jang, Y. C., "Study of optimum allocation in military engineering equipment for effective artillery position development operation", Master, pp.2016
- 정일한, "대안 부품을 고려한 다계층 시스템의 최적 중복 설계", 품질경영학회지, 43(1), pp.31~42 (2015), 한국품질경영학회[DOI]
- Kang, Y. H., "Scheduling Jobs with different Due-Date on Nonidentical Parallel Machine", Journal of Korean Institute of Industrial Engineers, 24(1), pp.37~50 (1998)
- 김대철, "병렬기계로 구성된 인쇄회로기판 제조공정에서의 스케쥴링에 관한 연구", 산업경영시스템학회지, 27(4), pp.141~146 (2004), 한국산업경영시스템학회
- 김동현, "표적 할당과 사격 순서의 동시 결정 문제를 위한 발견적 기법", 한국경영과학회지, 35(1), pp.47~65 (2010), 한국경영과학회
- Kim, Y. K., "Metaheuristic" (1997), Young-Ji
- 문정현, "포병화력 생존성지원을 위한 진지구축경로문제 연구", 대한산업공학회지, 37(3), pp.171~179 (2011), 대한산업공학회
- ROK Army Training Doctrine Command, "Data of Engineering Field(34-0-2)", Korea Military printing Institution, ~ (2013)
- Ronald, L. R., "Optimization in Operations Research" (1997), PrenticeHall
- Shah, R. K., "A New Approach for Automation of Location-based Earthwork Scheduling in Road Construction Projects", Automation in Construction, 43(2), pp.156~169 (2014)
- 원서경, "시스템 다이내믹스를 활용한 토공장비의 조합 모형 연구", 한국건설관리학회 논문집, 8(4), pp.194~202 (2007), 한국건설관리학회