변압기 권선공정에서의 수주 제작품의 단위공정 일정관리 시스템 개발과 다중회귀분석을 이용한 계획 리드타임 산출 및 관리 방안

Unit Process Scheduling System Development and Calculation and Control Method of Planned Leadtime Using Multiple Linear Regression under Make to Order Manufacturing System in Transformer Winding Process

0

조회

0

다운로드

0

인용

0

참고문헌

키워드

주제분류산업공학

초록

Ultra-high voltage transformer industry has characteristic of small quantity batch production system by other order processing unlike general mass production systems. In this industry, observance of time deadline is very important in market competitive power security and company continued existence. The transformer winding is a process that rolls a coil is coated with an electric insulation material in order to generate the required voltage using the voltage fluctuation. The winding process is very important production process in the extra-high voltage transformer manufacturing industry because winding process is core process that occupy weight about half of whole process and is process that decide current ratio of transformer. This paper proposes a statistical calculation and control method of planned leadtime on the basis of real data and informations for the A company in transformer winding process. Moreover, we develop unit process scheduling system.

Abstract

Ultra-high voltage transformer industry has characteristic of small quantity batch production system by other order processing unlike general mass production systems. In this industry, observance of time deadline is very important in market competitive power security and company continued existence. The transformer winding is a process that rolls a coil is coated with an electric insulation material in order to generate the required voltage using the voltage fluctuation. The winding process is very important production process in the extra-high voltage transformer manufacturing industry because winding process is core process that occupy weight about half of whole process and is process that decide current ratio of transformer. This paper proposes a statistical calculation and control method of planned leadtime on the basis of real data and informations for the A company in transformer winding process. Moreover, we develop unit process scheduling system.

참고문헌 (5)

  1. 박창권, "이종병렬기계로 구성된 변압기 권선공정의 생산일정계획", 산업경영시스템학회지, 26(2), pp.35~41 (2003), 한국산업경영시스템학회
  2. 박창권, "수주생산환경에서 생산일정계획 알고리듬 설계 및 정보시스템 구현:변압기 제조공정의 권선공정 적용사례", IE Interfaces, 16(2), pp.185~194 (2003)
  3. 서준영, "장비능력에 의존적인 처리시간을 가진 애로공정의 일정계획 수립(몰드 변압기 공장을 중심으로)", IE Interfaces, 14(4), pp.385~393 (2001)
  4. 정한일, "ILog를 활용한 금형 생산시스템의 일정계획 시스템 개발에 관한 연구", IE Interfaces, 13(4), pp.564~571 (2000)
  5. Ronald, E., Walpole, "Probability ad Statistics for Engineers and Scientists", pp.413~ (1993), Prentice Hall, Inc.

관련 논문AI추천

이 간행물의 다른 논문 (14건)