When monitoring an instrumental process, one often collects a host of data such as characteristic signals sent by a sensor in short time intervals. Characteristic data of short time intervals tend to be autocorrelated. In the instrumental processes often the practice of adjusting the setting value simply based on the previous one, so-called ‘adjacent point operation’, becomes more critical, since in the short run the deviations are harder to detect and in the long run they have amplified consequences. Stochastic modelling using ARIMA or AR models are not readily usable here. Due to the difficulty of dealing with autocorrelated data conventional practice is resorting to choosing the time interval where autocorrelation is weak enough then to using I-MR control chart to judge the process stability. In the autocorrelated instrumental processes it appears that using the Shewhart chart and the time interval data where autocorrelation is relatively not existent turns out to be a rather convenient and very useful practice to determine the process stability. However in the autocorrelated instrumental processes we intend to show that one would presumably do better using the EWMA control chart rather than just using the Shewhart chart along with some arbitrarily intervalled data,since the former is more sensitive to shifts given appropriate weights.
Abstract
When monitoring an instrumental process, one often collects a host of data such as characteristic signals sent by a sensor in short time intervals. Characteristic data of short time intervals tend to be autocorrelated. In the instrumental processes often the practice of adjusting the setting value simply based on the previous one, so-called ‘adjacent point operation’, becomes more critical, since in the short run the deviations are harder to detect and in the long run they have amplified consequences. Stochastic modelling using ARIMA or AR models are not readily usable here. Due to the difficulty of dealing with autocorrelated data conventional practice is resorting to choosing the time interval where autocorrelation is weak enough then to using I-MR control chart to judge the process stability. In the autocorrelated instrumental processes it appears that using the Shewhart chart and the time interval data where autocorrelation is relatively not existent turns out to be a rather convenient and very useful practice to determine the process stability. However in the autocorrelated instrumental processes we intend to show that one would presumably do better using the EWMA control chart rather than just using the Shewhart chart along with some arbitrarily intervalled data,since the former is more sensitive to shifts given appropriate weights.
참고문헌 (10)
- 조진형, "용해로 운전에서 Setting고정(4M 표준화)의 효율적 방안", 산업경영시스템학회지, 30(1), pp.96~104 (2007), 한국산업경영시스템학회
- Hong, E.P., "Statistical Design of CV-EWMA Control Chart", 석사, pp.2008
- Ji, S.S., "EWMA chart Application using the Transformation of the Exponential with Individual Observations", Journal of Society of Korea Industrial and Systems Engineering, 52, pp.337~345 (1999)
- Kim, K.W., "Bangbeoprongangeui" (2006), Bakyeongsa
- Kim, Y.J., "An Example on jointing SPC and APC for processes monitoring : ARIMA and PID-control", 석사, pp.2005
- Koo, J.H., "How to Control Non-conforming Rate in Manufacturing Process of High Autocorrelation : The Case of Display Monitor Glass", 박사, pp.2010
- Kumoh Institute, "Tonggye bunseokeul wihan Minitabeui Hwalyong" (2010), Geulnuri
- Michael, B.C., "Monitoring Process Mean and Variability with One Double EWMA Chart" (2010), Taylor and Francis
- Park, S.H., "Statistical Process Control" (2005), Minyeongsa
- 서정열, "ARMA-PL:Tackling Nested Periods and Linear Trend in Time Series Data", 산업경영시스템학회지, 33(2), pp.112~126 (2010), 한국산업경영시스템학회